-
1997 - A Vision Workshop was held.
-
2000 - A Feasibility Study was undertaken with
support from URC Wessex Trust, who have been involved at all stages.
-
The present plans gradually came together as the
challenges of the limited space were considered with the architect,
Keith Loveless.
-
Days of Prayer have been held so we have continued to
seek God’s will at each stage.
-
September 2001 - a Church Meeting decided in
principle to go ahead with the building plans, knowing that this would
be a huge challenge.
-
January 2003 - saw planning permission being granted
for the external changes.
-
November 2003 - there was a most encouraging
response at our Gift Day.
-
Autumn 2004 - we took the decision to phase the
project so as to take steps forward.
-
Spring 2005 - Building For The Future became a
reality with the completion of Phase 1; replacing the pews with chairs
and new carpeting.
-
Summer 2006 Phase 2 was carried out - a disabled ramp, new front and side
doors and new toilets (see pictures below) were installed.
-
Spring 2007- the pulpit went.
-
Summer 2007 - work on the new staging was
carried out.
-
Summer/Autumn 2008 - New multimedia facilities are
installed – i.e. digital projection and new PA system.
-
Summer/Autumn 2009 - New upstairs kitchen installed
and refurbishment of downstairs. Carpet and nosings to all the three staircases
-
Autumn 2010 - Removal of the pipe organ (to
create much needed ground floor storage space for equipment)
-
Spring 2011 - Creation of a much needed
storage are where the organ used to be
-
Summer 2011 - Splitting of the vestry
into two rooms; a quiet room and an office.
-
Autumn 2011 - New heating system.